Mosque Restoration Documentation & Handover
Mosque Restoration Documentation & Handover
A restoration project should leave a complete technical memory of the building. Future committees and professionals should be able to distinguish original condition, investigation, approved intervention and final as-built work without reconstructing the project from scattered emails.
1. Before-work record
- Rölöve Ölçümü
- Durum ve hasar haritaları
- Photo register
- Historic drawings and images
- Material / paint / structural investigations
- Mevcut tesisat sistemleri kaydı
2. Tasarım kayıtları
- Onaylı restorasyon çizimleri
- Structural and MEP documents
- Intervention schedules
- Malzeme teknik şartnameleri
- Uygulama çizimleri
- Authority or review approvals where applicable
3. Yapım kayıtları
| Record | Amaç |
|---|---|
| saha fotoğrafları | Show concealed and completed work |
| Denetim kayıtları | Confirm hold points and acceptance |
| Numune Onayları | Preserve colour, texture and material benchmark |
| Değişiklik Günlüğü | Explain departures from approved design |
| İlk İnceleme Kaydı | Record unexpected historic or technical findings |
4. As-built package
Update final geometry, service routes, access panels and specialist fabrication information. Mark where concealed fixings or future maintenance points are located.
5. Material and warranty register
Record manufacturer, product, finish, batch or colour reference where relevant, supplier contact, warranty and replacement information.
6. Bakım paketi
- Inspection priorities
- Cleaning restrictions
- Replacement lamps / drivers / filters
- Kubbe ve yağmur suyu drenajına erişim
- Timber and decorative-finish care
- Known watch points
7. Digital file structure
Separate mevcut durum, tasarım, Şantiye kaydı and as-built folders. Use date, discipline and revision in file names.
8. Handover meeting
Do not simply email a folder. Walk the mosque management team through access points, maintenance requirements, warranties and early-warning signs.
9. Sık sorulan sorular
Why keep photographs of concealed work?
They help future repairs avoid destructive investigation and show how supports, waterproofing or services were actually installed.
Should old superseded drawings be deleted?
No. Archive them clearly as superseded so the change history remains understandable.